# TS 110/35kV LOŠINJ

Substation LOŠINJ: B: up to 10 MW, 8.9 MW free. HEP ODS data on connecting power plants and battery storage, with the history of releases.

Category, existing network: B: up to 10 MW · Free capacity: 8.9 MW

## Figures

- **Category, existing network**: B: up to 10 MW
- **Category, with upgraded 110/x kV transformer**: D: more than 20 MW
- **Free capacity**: 8.9 MW
- **Added by the upgrade**: 20 MW
- **Existing users**: 1.1 MW
- **Users with a contract**: 16 MW
- **Requests in progress**: 0 MW
- **Total connection capacity**: 17 MW
- **Lowest daily consumption**: 5.8 MW
- **Transformers (MVA)**: 20 + 20
- **Planned transformers (MVA)**: 40 + 40
- **Voltage ratio**: 110/35 kV
- **Distribution area**: Elektroprimorje Rijeka
- **Location**: 44.58372, 14.40975
- **On the map**: [TS Lošinj](https://gridatlas.eu/en/?sel=osm%3Away%2F168544067&v=44.5836%2C14.4095%2C12)

## Substations it feeds

| Substation | Existing network | Free |
| --- | --- | --- |
| [TS 35/20kV LOŠINJ](https://gridatlas.eu/en/grid-capacity/ts-35-20kv-losinj/) | B: up to 10 MW | 7.5 MW |
| [TS 35/20kV LOŠINJ 2](https://gridatlas.eu/en/grid-capacity/ts-35-20kv-losinj-2/) | B: up to 10 MW | 7.2 MW |
| [TS 35/20kV OSOR](https://gridatlas.eu/en/grid-capacity/ts-35-20kv-osor/) | A: up to 5 MW | 4 MW |
| [TS 35/10kV SILBA](https://gridatlas.eu/en/grid-capacity/ts-35-10kv-silba/) | A: up to 5 MW | 4 MW |

## Category across releases

| Release | Existing network | Free |
| --- | --- | --- |
| 1 November 2026 (v6) | B: up to 10 MW | 8.9 MW |

## Source and disclaimer

- [Show the place on the map](https://gridatlas.eu/en/?v=44.5837%2C14.4098%2C12)
- [Free capacity in the distribution grid (HEP ODS)](https://gridatlas.eu/en/grid-capacity/)

Source: HEP ODS, kapaciteti.hep.hr, reused with HEP ODS's permission. HEP ODS keeps the information as current as it can but cannot guarantee it is timely or accurate when a connection request (EOTRP) is filed; the data is for information only and guarantees no connection. A category is a band, and the free capacity of a 35/x kV substation is also limited by the substation above it, so capacities are never added up.

State of the data: 1 November 2026 (v6).

- [HEP ODS's map: kapaciteti.hep.hr](https://kapaciteti.hep.hr/)

---

GridAtlas

- Page: https://gridatlas.eu/en/grid-capacity/ts-110-35kv-losinj/
- Data from 13 November 2026
- Data: ODbL, CC BY and partly CC BY-NC, with attribution; downloads as a whole are non-commercial. Code: MIT.
- How to cite (APA): GridAtlas. (2026, November 13). TS 110/35kV LOŠINJ [Data set]. https://gridatlas.eu/en/grid-capacity/ts-110-35kv-losinj/