# TS 220/110/30kV BILICE

Substation BILICE: D: more than 20 MW, 75 MW free. HEP ODS data on connecting power plants and battery storage, with the history of releases.

Category, existing network: D: more than 20 MW · Free capacity: 75 MW

## Figures

- **Category, existing network**: D: more than 20 MW
- **Category, with upgraded 110/x kV transformer**: D: more than 20 MW
- **Free capacity**: 75 MW
- **Added by the upgrade**: 0 MW
- **Existing users**: 45 MW
- **Users with a contract**: 28 MW
- **Requests in progress**: 3.8 MW
- **Total connection capacity**: 78 MW
- **Lowest daily consumption**: 26 MW
- **Transformers (MVA)**: 63 + 63 + 63
- **Planned transformers (MVA)**: 63 + 63 + 63
- **Voltage ratio**: 220/110/30 kV
- **Distribution area**: Elektra Šibenik
- **Location**: 43.75590, 15.90444
- **On the map**: [TS Bilice](https://gridatlas.eu/en/asset/osm-way-162022271/)

## Substations it feeds

| Substation | Existing network | Free |
| --- | --- | --- |
| [TS 30/10/6.3kV LOZOVAC](https://gridatlas.eu/en/grid-capacity/ts-30-10-6-3kv-lozovac/) | no capacity | 0 MW |
| [TS 30/10kV PODI](https://gridatlas.eu/en/grid-capacity/ts-30-10kv-podi/) | no capacity | 0 MW |
| [TS 30/10kV PRIMOŠTEN](https://gridatlas.eu/en/grid-capacity/ts-30-10kv-primosten/) | A: up to 5 MW | 3.4 MW |
| [TS 30/10kV ROGOZNICA](https://gridatlas.eu/en/grid-capacity/ts-30-10kv-rogoznica/) | A: up to 5 MW | 0.7 MW |
| [3RS18 RS 30 kV VE ORLICE](https://gridatlas.eu/en/grid-capacity/3rs18-rs-30-kv-ve-orlice/) | no capacity | 0 MW |
| [TS 30/10kV ŠIBENIK 1](https://gridatlas.eu/en/grid-capacity/ts-30-10kv-sibenik-1/) | C: up to 20 MW | 15 MW |
| [TS 30/10kV ŠIBENIK 3](https://gridatlas.eu/en/grid-capacity/ts-30-10kv-sibenik-3/) | C: up to 20 MW | 10 MW |
| [TS 30/10kV VODICE](https://gridatlas.eu/en/grid-capacity/ts-30-10kv-vodice/) | C: up to 20 MW | 14 MW |

## Category across releases

| Release | Existing network | Free |
| --- | --- | --- |
| 1 November 2026 (v6) | D: more than 20 MW | 75 MW |

## Source and disclaimer

- [Show the place on the map](https://gridatlas.eu/en/?v=43.7559%2C15.9044%2C12)
- [Free capacity in the distribution grid (HEP ODS)](https://gridatlas.eu/en/grid-capacity/)

Source: HEP ODS, kapaciteti.hep.hr, reused with HEP ODS's permission. HEP ODS keeps the information as current as it can but cannot guarantee it is timely or accurate when a connection request (EOTRP) is filed; the data is for information only and guarantees no connection. A category is a band, and the free capacity of a 35/x kV substation is also limited by the substation above it, so capacities are never added up.

State of the data: 1 November 2026 (v6).

- [HEP ODS's map: kapaciteti.hep.hr](https://kapaciteti.hep.hr/)

---

GridAtlas

- Page: https://gridatlas.eu/en/grid-capacity/ts-220-110-30kv-bilice/
- Data from 13 November 2026
- Data: ODbL, CC BY and partly CC BY-NC, with attribution; downloads as a whole are non-commercial. Code: MIT.
- How to cite (APA): GridAtlas. (2026, November 13). TS 220/110/30kV BILICE [Data set]. https://gridatlas.eu/en/grid-capacity/ts-220-110-30kv-bilice/