GridAtlas Regional energy map

TS 110/10kV 4TS 29 SOPOT

Category, existing network: D: more than 20 MW · Free capacity: 88 MW

Figures

Category, existing network
D: more than 20 MW
Category, with upgraded 110/x kV transformer
D: more than 20 MW
Free capacity
88 MW
Added by the upgrade
0 MW
Existing users
5.8 MW
Users with a contract
0.4 MW
Requests in progress
0.4 MW
Total connection capacity
6.5 MW
Lowest daily consumption
15 MW
Transformers (MVA)
40 + 40 + 40
Planned transformers (MVA)
40 + 40 + 40
Voltage ratio
110/20/10 kV
Distribution area
Elektra Zagreb
Location
45.77047, 15.98444
On the map
TS Sopot

Category across releases

ReleaseExisting networkFree
1 November 2026 (v6)D: more than 20 MW88 MW

Source and disclaimer

Source: HEP ODS, kapaciteti.hep.hr, reused with HEP ODS's permission. HEP ODS keeps the information as current as it can but cannot guarantee it is timely or accurate when a connection request (EOTRP) is filed; the data is for information only and guarantees no connection. A category is a band, and the free capacity of a 35/x kV substation is also limited by the substation above it, so capacities are never added up.

State of the data: 1 November 2026 (v6).

How to cite

For publication: Source: GridAtlas (gridatlas.eu); as of November 13, 2026.

APA: GridAtlas. (2026, November 13). TS 110/10kV 4TS 29 SOPOT [Data set]. https://gridatlas.eu/en/grid-capacity/ts-110-10kv-4ts-29-sopot/