Category, existing network: D: more than 20 MW · Free capacity: 45 MW

Figures

Category, existing network
D: more than 20 MW
Category, with upgraded 110/x kV transformer
D: more than 20 MW
Free capacity
45 MW
Added by the upgrade
0 MW
Existing users
0.1 MW
Users with a contract
0.2 MW
Requests in progress
0.1 MW
Total connection capacity
0.4 MW
Lowest daily consumption
5.6 MW
Transformers (MVA)
40 + 40
Planned transformers (MVA)
40 + 40
Voltage ratio
110/10(20) kV
Distribution area
Elektrojug
Location
42.64292, 18.12274

Category across releases

ReleaseExisting networkFree
1 November 2026 (v6)D: more than 20 MW45 MW

Source and disclaimer

Source: HEP ODS, kapaciteti.hep.hr, reused with HEP ODS's permission. HEP ODS keeps the information as current as it can but cannot guarantee it is timely or accurate when a connection request (EOTRP) is filed; the data is for information only and guarantees no connection. A category is a band, and the free capacity of a 35/x kV substation is also limited by the substation above it, so capacities are never added up.

State of the data: 1 November 2026 (v6).

How to cite

For publication: Source: GridAtlas (gridatlas.eu); as of November 13, 2026.