GridAtlas Regional energy map

TS 110/20/10kV KNEGINEC

Category, existing network: no capacity

Figures

Category, existing network
no capacity
Category, with upgraded 110/x kV transformer
C: up to 20 MW
Added by the upgrade
15 MW
Existing users
12 MW
Users with a contract
12 MW
Requests in progress
4.1 MW
Total connection capacity
28 MW
Lowest daily consumption
3.4 MW
Transformers (MVA)
20 + 20
Planned transformers (MVA)
40 + 40
Voltage ratio
110/20/10 kV
Distribution area
Elektra Varaždin
Location
46.25936, 16.37548
On the map
TS Kneginec

Category across releases

ReleaseExisting networkFree
1 November 2026 (v6)no capacity

Source and disclaimer

Source: HEP ODS, kapaciteti.hep.hr, reused with HEP ODS's permission. HEP ODS keeps the information as current as it can but cannot guarantee it is timely or accurate when a connection request (EOTRP) is filed; the data is for information only and guarantees no connection. A category is a band, and the free capacity of a 35/x kV substation is also limited by the substation above it, so capacities are never added up.

State of the data: 1 November 2026 (v6).

How to cite

For publication: Source: GridAtlas (gridatlas.eu); as of November 13, 2026.

APA: GridAtlas. (2026, November 13). TS 110/20/10kV KNEGINEC [Data set]. https://gridatlas.eu/en/grid-capacity/ts-110-20-10kv-kneginec/