TS 110/35/20/10kV SLAVONSKI BROD 2-BJELIŠ

Category, existing network: A: up to 5 MW · Free capacity: 4.3 MW

Figures

Category, existing network
A: up to 5 MW
Category, with upgraded 110/x kV transformer
A: up to 5 MW
Free capacity
4.3 MW
Added by the upgrade
0 MW
Existing users
3.2 MW
Users with a contract
33 MW
Requests in progress
3.2 MW
Total connection capacity
40 MW
Lowest daily consumption
4.1 MW
Transformers (MVA)
40
Planned transformers (MVA)
40 + 40
Voltage ratio
110/35/20/10 kV
Distribution area
Elektra Slavonski Brod
Location
45.14972, 18.04944
On the map
TS Slavonski Brod 2

Substations it feeds

SubstationExisting networkFree
TS 35/10kV BROD IIIA: up to 5 MW4.3 MW
TS 35/10kV BROD IVA: up to 5 MW4.3 MW

Category across releases

ReleaseExisting networkFree
1 November 2026 (v6)A: up to 5 MW4.3 MW

Source and disclaimer

Source: HEP ODS, kapaciteti.hep.hr, reused with HEP ODS's permission. HEP ODS keeps the information as current as it can but cannot guarantee it is timely or accurate when a connection request (EOTRP) is filed; the data is for information only and guarantees no connection. A category is a band, and the free capacity of a 35/x kV substation is also limited by the substation above it, so capacities are never added up.

State of the data: 1 November 2026 (v6).

How to cite

For publication: Source: GridAtlas (gridatlas.eu); as of November 13, 2026.

APA: GridAtlas. (2026, November 13). TS 110/35/20/10kV SLAVONSKI BROD 2-BJELIŠ [Data set]. https://gridatlas.eu/en/grid-capacity/ts-110-35-20-10kv-slavonski-brod-2-bjelis/