TS 110/35kV DELNICE
Category, existing network: B: up to 10 MW · Free capacity: 8.9 MW
Figures
- Category, existing network
- B: up to 10 MW
- Category, with upgraded 110/x kV transformer
- D: more than 20 MW
- Free capacity
- 8.9 MW
- Added by the upgrade
- 20 MW
- Existing users
- 13 MW
- Users with a contract
- 1.7 MW
- Requests in progress
- 3.1 MW
- Total connection capacity
- 18 MW
- Lowest daily consumption
- 6.7 MW
- Transformers (MVA)
- 20 + 20
- Planned transformers (MVA)
- 40 + 40
- Voltage ratio
- 110/35 kV
- Distribution area
- Elektroprimorje Rijeka
- Location
- 45.39315, 14.80729
- On the map
- TS Delnice
Substations it feeds
| Substation | Existing network | Free |
|---|---|---|
| TS 35/6.3kV CHE FUŽINE | no capacity | 0 MW |
| TS 35/6.3kV CHE LEPENICA | no capacity | 0 MW |
| TS 35/20kV DELNICE | B: up to 10 MW | 5.5 MW |
| TS 35/6.3kV DRVENJAČA | B: up to 10 MW | 8 MW |
| TS 35/20kV GEROVO | A: up to 5 MW | 1 MW |
| TS 35/20kV KUPJAK | B: up to 10 MW | 5.8 MW |
| TS 35/0.4kV RAZROMIR | no capacity | 0 MW |
| TS 35/20kV VRATA | B: up to 10 MW | 6.5 MW |
Category across releases
| Release | Existing network | Free |
|---|---|---|
| 1 November 2026 (v6) | B: up to 10 MW | 8.9 MW |
Source and disclaimer
Source: HEP ODS, kapaciteti.hep.hr, reused with HEP ODS's permission. HEP ODS keeps the information as current as it can but cannot guarantee it is timely or accurate when a connection request (EOTRP) is filed; the data is for information only and guarantees no connection. A category is a band, and the free capacity of a 35/x kV substation is also limited by the substation above it, so capacities are never added up.
State of the data: 1 November 2026 (v6).
How to cite
For publication: Source: GridAtlas (gridatlas.eu); as of November 13, 2026.
APA: GridAtlas. (2026, November 13). TS 110/35kV DELNICE [Data set]. https://gridatlas.eu/en/grid-capacity/ts-110-35kv-delnice/