TS 110/35kV METERIZE
Category, existing network: D: more than 20 MW · Free capacity: 41 MW
Figures
- Category, existing network
- D: more than 20 MW
- Category, with upgraded 110/x kV transformer
- D: more than 20 MW
- Free capacity
- 41 MW
- Added by the upgrade
- 0 MW
- Existing users
- 0.3 MW
- Users with a contract
- 2.7 MW
- Requests in progress
- 0.5 MW
- Total connection capacity
- 3.5 MW
- Lowest daily consumption
- 4.2 MW
- Transformers (MVA)
- 40 + 40
- Planned transformers (MVA)
- 40 + 40
- Voltage ratio
- 110/35 kV
- Distribution area
- Elektrodalmacija Split
- Location
- 43.52918, 16.50085
- On the map
- TS Meterize
Substations it feeds
| Substation | Existing network | Free |
|---|---|---|
| TS 35/10kV BRODOGRADILIŠTE | C: up to 20 MW | 14 MW |
| TS 35/10kV KLIS | B: up to 10 MW | 6.8 MW |
Category across releases
| Release | Existing network | Free |
|---|---|---|
| 1 November 2026 (v6) | D: more than 20 MW | 41 MW |
Source and disclaimer
Source: HEP ODS, kapaciteti.hep.hr, reused with HEP ODS's permission. HEP ODS keeps the information as current as it can but cannot guarantee it is timely or accurate when a connection request (EOTRP) is filed; the data is for information only and guarantees no connection. A category is a band, and the free capacity of a 35/x kV substation is also limited by the substation above it, so capacities are never added up.
State of the data: 1 November 2026 (v6).
How to cite
For publication: Source: GridAtlas (gridatlas.eu); as of November 13, 2026.
APA: GridAtlas. (2026, November 13). TS 110/35kV METERIZE [Data set]. https://gridatlas.eu/en/grid-capacity/ts-110-35kv-meterize/